July 27th - Overhead plumbing completed, framing began!
Published July 27, 2026
optimizing
We are approximately 2 weeks ahead of schedule and below budget -- praise God! Overhead plumbing in the attic space has been completed, and metal framing has begun this week.
Meet our construction foreman, George Hernandez. He has been instrumental in keeping our renovation project moving forward smoothly. We thank God for him and his diligence!